TUZLA Power Plant

Tuzla

Installed boilers:

Boiler Type Qty Capacity [t/h] /Output Power [MW] Steam Temperature [oC] Steam Pressure [MPa] Fuel Start-up Year
OB 3 650 t/h 540 16,2 lignite 1966 - 1976

Installed dust extraction equipment:

Heat or electricity power Boiler number Flue gas flow [m^3/h] Guaranteed emission [mg/m^3] Fuel Start-up Year
215 MW K6 1 050 000 <30 lignite 2013

Installed boiler modernization / NOx reduction:

Boiler Type Boiler number Description Reduction [%] NOx emission [g/GJ] Start-up Year
OP-650b   Tangential furnace, low-emission swirl burners, new heat transfer surfaces   NOx<450 mg/mn3 2002